Hughes, W.
ORCID: https://orcid.org/0000-0002-0304-8136, Hillebrandt, P. and Murdoch, J.
(2000)
The impact of contract duration on the cost of cash retention.
Construction Management and Economics, 18 (1).
pp. 11-14.
ISSN 0144-6193
doi: 10.1080/014461900370906
Abstract/Summary
Cash retention is a common means of protecting an employer from a contractor's insolvency as well as ensuring that contractors finish the work that they start. Similarly, contractors withhold part of payments due to their sub-contractors. Larger contracts tend to be subjected to smaller rates of retention. By calculating the cost of retention as an amount per year of a contract, it is shown that retention is far more expensive for firms whose work consists of short contracts. The extra cost is multiplied when the final payment is delayed, as it often is for those whose work takes place at the beginning of a project. This may explain why it is that main contractors are a lot less interested than sub-contractors in alternatives to cash retention, such as retention bonds
Altmetric Badge
| Item Type | Article |
| URI | https://reading-clone.eprints-hosting.org/id/eprint/4300 |
| Identification Number/DOI | 10.1080/014461900370906 |
| Refereed | Yes |
| Divisions | Science > School of the Built Environment > Organisation, People and Technology group |
| Uncontrolled Keywords | bonds; cash flow; contract; finance; retention |
| Publisher | Taylor & Francis |
| Download/View statistics | View download statistics for this item |
Downloads
Downloads per month over past year
University Staff: Request a correction | Centaur Editors: Update this record
Download
Download